Monday 9 August 2010

Camberwell South Primary School

New Performing Arts Building

PROJECT ARCHITECT (2009-current)

Taylor Oppenheim Architects, supervised by Michael Taylor (Company Director)
Project budget $2.2M

Floor area 850sqm


Brief Description 

  • This project involves redeveloping part of Camberwell South Primary School site to build a new Performing Arts building. Project funding came as part of the government’s Non-Template Building the Education Revolution (BER) program.



Competencies Demonstrated
  • Integrated schematic design, design development process. 
  • Liason with school & DEECD. 
  • Work with quantity surveyor to manage project budget & contingency sum through design process to tendering. 
  • Contract documentation & coordination with specialist consultants. 
  • Prepare technical specification & schedules. 
  • Administer tender process, address tender queries, prepare tender report & recommendation. 
  • Prepare building contract. 
  • Manage contract administration process. 
  • Assess, manage and negotiate contractor’s progress claims, variations, weather delays and extension of time. 
  • Coordinate with specialist consultants in attending to contractor’s site query and RFIs. 
  • Monitor contingency sum and projected date for practical completion throughout construction.

Concrete pouring, Camberwell South PS
Artist Impression

2 comments:

Anonymous said...

cool project
have time visit Me
< http://www.sugarvod.com/?refaff=16670

lcrenovation said...

Article ideas very clear . Your writing style is very unique. I very much appreciate the articles you write. Thanks a lot for sharing. Please visit to know
https://www.lcrenovation.co.uk/loft-conversion-in-bermondsey/
House Renovations in Bermondsey